Target polarization data repository.
Target cryogenics data repository.
Programs for analysing NMR-signals and cryogenics data.
Small utilities: dcsread, ptread, shiftlist and rfindcalc.
The target operated well from 18th of June to 18th of September. There were two transverse polarization mode periods with microwave polarization reversal in the middle. First of them was from 3rd of August to 12th of August. Second one was from 11th of September to 18th of September. In the beginning the upstream target cell had negative polarization while the downstream target cell had positive polarization. After the microwave polarization reversal on 6 - 8th of August the upstream target cell had positive polarization while the downstream cell had negative polarization. During the run the polarization was lost 4 times due to loss of magnetic field. In the run 2002 about 405 eight hour target shifts were done. 342 of these were during the beam time, 42 before and 21 after. Thanks to the about 50 persons from the collaboration who took part in the target shifts. Preliminary polarization 2002.. Online average polarization 2002..
For the year 2001 the old magnet from the SMC experiment was installed on the platform. A new microwave cavity fitting inside the magnet 265 mm diameter bore was manufactured (May - Jul 2001). The cavity has 0.5 mm down stream end window made of copper. The two target halves are separated by a microwave stopper made from 0.1 mm copper foil. The mixing chamber is the same as in the SMC experiment. With the two target cells (each 60 cm long and diameter 3 cm) separated by 10 cm distance in the center of the solenoid this leads to an acceptance of 69 mrad.
Big effort between CERN and Saclay was needed to get the magnet work in very short time (May - Aug 2001). The target material 6LiD from Bochum was successfully loaded inside the mixing chamber (Aug 2001). The first polarization runs (Sep 2001) have resulted to negative and positive polarizations from 45 to 50 % ( zipped ppt-file ). To confirm these values more NMR data is being collected.
A test solenoid was used to determine how the magnetic poles correspond to the magnetic field direction. The photos are here.
Date | Upstream | Downstream | Field direction |
---|---|---|---|
2002 July 22 | South | North | ups <- dws |
2003 July 3 | South | North | ups <- dws |
2004 June 11 | South | North | ups <- dws |
2006 July 26 | North | South | ups -> dws |
The Canadian Geological Survey definition of the North Magnetic Pole is here
The spin magnetization poles can be determined from the known solenoid current sign and from the sign of the polarization as follows:
positive polarization | negative polarization | positive polarization | negative polarization | |
---|---|---|---|---|
positive current 2002 - 2004 | South-North | North-South | ups <- dws | ups -> dws |
negative current 2002 - 2004 | North-South | South-North | ups -> dws | ups <- dws |
positive current 2006 | North-South | South-North | ups -> dws | ups <- dws |
negative current 2006 | South-North | North-South | ups <- dws | ups -> dws |
Here is a side view of the magnet.. The solenoid is powered with the Danfysik power supply while for the dipole coil we use the old Drusch power supply from SMC. The magnet has a Quench Back Heater system to cause a forced quench if quench in some part of the solenoid is detected. The burst disk gives the ultimate safety in sudden evaporation of LHe. The suspension system will keep the solenoid in place even when SM1 is powered and a large torque is acting on the coil. The magnet is connected to the dilution cryostat from the upstream flange.
System integration between Oxford Instruments magnet and CERN facilities is being discussed. Here is information about the old SMC cryogenic system. COMPASS will use the old Drusch power supply for the dipole magnet and the safety interlock unit to prevent energizing of dipole if solenoid has more that 1/3 of its maximum field.
Safety issues concerning the magnet installation have been discussed with TIS division . Mainly this concerns the pressure vessel safety code D2, magnetic field and operation safety.
The conical cavity inside the magnet has 100 um thick Cu foil at its end. Such a thin foil can not stand any practical pressure difference. Thus the cavity vacuum will be shared with Oxford magnet vacuum. This is different from the SMC experiment where the cavity was isolating the vacuum outside of the mixing chamber from magnet vacuum and worked as an extra protection in case that the glass fiber mixing chamber for some reason starts to leak. This could happen for example when the target material is being loaded. In this procedure there are mechanical forces to the mixing chamber.
Since the muon beam is now focused to 30 mm diameter a smaller diameter
of mixing
chamber can be used. The volume of target material and helium surrounding it
was the same for the SMC target. Thus the mixing chamber could be made
to 45 mm in diameter. Thus a new glass fiber mixing chamber is being prepared.
It has to be leak and pressure tested before it can be accepted. In normal
operation the mixing chamber has to stand + 1 atm pressure.
Leak testing of the new mixing chamber showed no
leaks at room temperature (Sep 2000). Unfortunately in cooling down with
LN2, two of the three glass fiber tubes started to leak. They were inspected
after opening the test vacuum vessel and cracks were seen close to the
end hemisphere.
Leak and flow tests at room temperature showed (Dec 1999 - Jan 2000) that the cryostat is ok. One epoxy feed through from still was leaking to vacuum, but was easy to fix. A cryogenic leak test was be done in March 2001. The leak rate stayed at 10^-9 mbar l/s and isolation vacuum pressure below 10^-7 mbar during the one week period that the cryostat was cold. The minimum temperature obtained was only about 0.25 K due to missing 4 K radiation shield, i.e. only 80 K radiation shield was used. More careful technical run will be needed to verify proper operation of heat exchangers and to check thermometer calibration.
Due to new focusing of the muon beam from 50 mm diameter to 30 mm diameter, the polarized target had to be moved 20 m down stream compared to its position in the SMC experiment. A new pump hut had to be constructed and new pumping lines welded.
The cooling water circuit for the pumps and pressurized air for electro-pneumatic valves are both ready (June 2000). The roots blowers were tested (Feb - Mar 2001). The test included purging by pumping dry nitrogen for several days, helium leak tests and pumping of helium gas for a week to see how much air impurity is accumulated into LN2 trap. AT/ECR/Cryolab was responsible of the testing.
4He pumps were tested after the roots blowers. The 4He pumping and exhaust tubes were installed with bypass and overpressure valves and manometers.
The control panel has new purifier cartridges and the LN2 trap new charcoal in it. Both are kept under vacuum when the dilution cryostat is not run. The trap and purifiers were also leak tested before they were put in to use.
The 3He tanks were connected to control panel. A new hermetic pump from Alcatel 2033H was bought for reliable recovery of 3He (which has value of about 250 kCHF) in all conditions. Mixture inventory was made 15th of March 2001 by AT/ECR/Cryolab. 1387 l NTP of 3He gas was found. In addition we have 7198 l NTP of 4He gas.
The cryostat needs 15 - 40 l/h depending on the 3He flow and the magnet about 10 - 20 l/h at full field. The helium recovery goes back to the cold box. In case of a quench the evaporating helium gas is vented to the experimental hall through the over pressure valves of SMC magnet.
See status
of COMPASS cold box for information about liquid helium available for
target.
The control software for the target cryostat and NMR is done with LabVIEW in Windows NT. It controls and monitors cryostat and NMR system through GPIB bus and a VME crate. For the NMR a dedicated PC is installed. During the cool down of the cryostat the PC was used to record the different parameters of the cryostat. The present status of the target can be seen on the web. For the SMC magnet the old Sun system is used for the control.
See Bochum Polarized Target Group. They are working on 6LiD.
See COMPASS web camera if
you want to know what is happening right now in the experimental area.
(tell me the missing names)
W. Meyer
G. Reicherz
S. Goertz
A. Meier
I. Llorente-Garcia
L. Dufay
A. Vacca
L. Mao
G. Vandoni
C. Policella
J-M Rieubland
T. Niinikoski
P. Berglund
J. Koivuniemi
I. Daito
N. Doshita
T. Hasegawa
N. Horikawa
S. Ishimoto
T. Iwata
K. Kondo
T. Matsuda
N. Takabayashi
Michael Finger
Miroslav Finger
S. Neliba
A. Srnka
J. Ball
J-M Le Goff
A. Magnon
C. Marchand