The construction of all the 14 chambers will be done in the
INFN laboratory in Trieste.
To match the schedule illustrated above
we have estimated the following manpower
(HLT - high-level technician):
- 3 technicians (1 HLT,) full time for prototype modifications,
assistance during tests and for chamber design in 96
- 4 technicians (1 HLT,) full time for mechanical constructions and
assistance during tests in period 97 - 99
- 2 technicians (1 HLT) 50% time during 97
for printed-board circuits design,
prototype construction and tests
- 1 technician (1 HLT) 50% time during 98 to follow
production by industry.
These resources should be available in Trieste for COMPASS.
Lars Schmitt
Wed May 22 16:44:09 METDST 1996