Responsibilities and Manpower

The responsibilities for the different subsystems will be shared and manpower allocated as follows:

  table1013
Table 3.13:   Sharing of the responsibilities.

At CERN a full-time coordinator and two technicians familiar with CERN will be needed during the modifications of the vacuum system and platform, assembly and tests of the dilution refrigerator, installation and tests of the magnet and final mounting and tests of the target. The upgrade of the NMR and DAQ systems requires 1 to 2 students for one year. During the assembly and tests of the dilution refrigerator at least two additional persons are needed. During the installation and tests of the magnet some manpower will be provided by the manufacturer. A microwave expert will be needed for the modification of the microwave system. At least 5 persons are needed during the test run with the complete target setup.