After separate tests of the magnet with the warm bore in the hall 888 and leak testing the dilution refrigerator in the clean area they will be combined for a final test run. After the cooldown of the complete system, final leak tests will be made and the cooling power of the dilution refrigerator and the microwave power will be measured. Afterwards the target material (NH or LiD) will be loaded, the NMR system tuned and polarization tests will be done.
Table 3.7:
Schedule for the final target tests.