Minutes from target meeting held July 25 2014 in 892-2-009 These minutes are available also from: http://wwwcompass.cern.ch/compass/detector/target/Minutes/2014/ a) Helium-4 pumping line leak located to the Helicoflex o-rings. The metal surface had been damaged during the installation. Helium leak test helium-3 return line, cavity pumping line, vertical/horizontal screen lines and separator outlet. b) The dilution cryostat tape heaters were installed. c) Martin: new web page interface to the COMPASS MySQL database under development. d) Fabrice: diffusion pump butterfly valve failed to open due to too small diameter in the connection piece to the magnet vacuum port. The flange needs to be machined and welding moved from inside to outside. Differential pressure gauge is going to be used as a helium level meter on the magnet. Helium gas recovery line heaters were installed and cabled. The helium buffer dewar pressure test is going to be done soon. e) Kaori: test MySQL database connection to the COMPASS online database. Test NMR Q-meters to see the Q-curve. Test analog voltage extension cables between control room and target platform.