Minutes from target meeting held May 23 2014 in 892-1-B09 These minutes are available also from: http://wwwcompass.cern.ch/compass/detector/target/Minutes/2014/ a) The new helium-3 pumping line from the concrete wall to the dilution cryostat was installed on Tuesday with o-rings. Final fixing of the flanges and bellows need to be still done. b) Mount the two large water cooled heat exchangers on the helium-3 roots blowers on Wednesday and Thursday. Start pumping vacuum to the roots pumps for helium leak testing. c) The normal cooling water back in the experimental zone on Wednesday. The control room air conditioning starts to provide normal temperatures around 20 C. d) Fabrice: two analog 4-20 mA signals will be provided from the liquid helium dewar for monitoring the level with a PLC. The magnet cable and power cable patch panel design done and waiting for production. The PH/DT is starting to produce the missing cables between the control racks and magnet. e) The cable tray on the Saleve side concrete wall for the cables going to the control room was discussed. f) Kaori: compatibility issue with present LabVIEW version and the PXI crate used in the NMR DAQ. The possibility to use a DIM server to publish the data to the COMPASS DCS system is under study. Waiting for the new thin UT034 coaxial cable for the target cells. g) Norihiro: the servomotor microcontrollers were updated with a new version of firmware. New cables between the control room and the dilution cryostat need to be produced for the servomotors.