Minutes from target meeting held August 15 2014 in 892-2-009 These minutes are available also from: http://wwwcompass.cern.ch/compass/detector/target/Minutes/2014/ a) Pull PT100 thermometer cables. Three thermometers available now: horizontal screen, dilution cyrostat top flange and helium-3 pumping line top. Connect LHe control cables and test opening of the electropneumatic valves. Limit switches work too. Install air heaters and test air blowers. Fix short in two tape heater cable connections to the power cable. b) Run helium-3 roots pumps for 18 hours. Fix water leak in the flow switch. The ELMB17 station in the pump room is available for monitoring the water cooled heat exchanger temperatures. c) The resistive thermometers TDR2, TDR5 and TPR8 have a problem in the cabling or in the connectors. One of the wires is disconnected when measuring from the control room panel. The wires inside dilution cryostat are ok. d) Johannes: magnet cabling and cable testing is going on. New vertex detector installed downstream of the target on the hadron absorber concrete shielding blocks. e) Genki: install analog voltage panel in the control room and start to solder cables to the pressure displays. f) Jan: modify ptread code so that the produced data can be inserted to many remote MySQL databases at the same time.