Minutes from target meeting held July 11 2014 in 892-1-D20 These minutes are available also from: http://wwwcompass.cern.ch/compass/detector/target/Minutes/2014/ a) Leak test helium-3 pumping line. Small diffusive leaks found from two DN250 Silicone rubber MVQ o-rings. b) Switch on all the helium-3 roots blowers for testing. The pump room temperature reached +27 C in six hours. Thus the air conditioning unit is not operating normally. c) Fabrice: magnet power cables between the platform, patch panel and control zone already installed. Work going on for the signal cables. The extra length of the signal cables will be stored under the target platform on Jura side. Small modification of the cable trays going on. The magnet gas panel needs a small modification. The normal power and diesel network are operational in the control area. Interconnection between the racks has been already done. d) Fabrice: the isolation vacuum diffusion pump system electropneumatic control system being installed. The diffusion pump oil needs to be put into the pump. e) Pressure test of the 2000 l LHe buffer dewar on the target platform planned for next week. f) Kaori: testing microwave system with Yuri. At the end of the wave guide at target platform 2 W measured with the Nagoya EIO tube power supply while the Yamagata power supply gave 5 W with a second EIO tube. The power reflected from the dilution cryostat feedthroughs could also be measured. The EIO tube water cooler temperature could be read to a computer. g) Kaori: test MySQL database connection from the NMR computer. The communication between the NMR computer and the magnet power converter control system needs to be tested. h) Small modification proposed by CERN workshop to the drawing NA58PT20131106-1 for easier electron beam welding of the 100 um stainless steel vacuum window.