Minutes from target meeting held January 19 2012 in 892-2-009 These minutes are available also from: http://wwwcompass.cern.ch/compass/detector/target/Minutes/2012/ a) On Monday disconnect and unmount the cavity line, helium-3/4 return lines and helium-4 pumping line from the concrete wall to the top of the dilution cryostat. On Tuesday unmount the big helium-3 pumping line. Problem during the removal due to broken crane and its repair intervention. The pumping ports and pipes closed with aluminum foil. Switch off all the remaining pressure gauges and the PLC on Wednesday morning. Start to remove the cables going to the target platform. All the cables removed by Thursday noon. Remove the target loading platform and dilution cryostat evacuation pumps on Friday. b) Yuri: drain water from the microwave EIO generator tube coolers. Air spray would be useful for cleaning the pipes. c) Kaori: the EIO tube operation time in 2011 about 400 - 600 hours.