Minutes from target meeting held March 19 2010 in 892-2-009 These minutes are available also from: http://wwwcompass.cern.ch/compass/detector/target/Minutes/2010/ a) Produce two more new SMA feed-throughs for target holder now with new Stycast 2850 and catalyst 24 LV. No leak observed in the assembled feed-through after two rapid cool downs to LN2. Background leak level was below 10^-9 mbar l/s. b) Fabrice: stop filling magnet with LHe on Friday. On Monday 70 K coil temperature reached. Test new helium-4 pumps on Monday with full 2000 m^3/h pumping speed and pump inlet pressure set to 1 mbar. TPO4 reached 10 kohm and later 13 - 15 kohm with different needle valve positions. Pumps are now ready for run 2010. Repair pump room air conditioning on Friday. c) Yuri: test new microwave PSU. EIO output power at control room about 18 W. Check PSU interlock circuit. d) Angelo: fluka simulations of absorber with polarized target. See http://wwwcompass.cern.ch/twiki/bin/view/Drell_Yan/FutureAbsorber