Minutes from target meeting held January 18 2007 in 892-1-B09 These minutes are available also from: http://wwwcompass.cern.ch/compass/detector/target/Minutes/2007/ a) The safety valves were unmounted on Wednesday and sent to Safety Commission for inspection. The magnet safety valve was installed back on same day. b) The carbon filter after the 4He rotary pump was opened. On small sample of the carbon pellets it is difficult to see oil on the surface. The oil on bottom may come from spilling when the pumps are initially started and they work with maximum power. When the zeolite filter material was replaced with the carbon it looked also dry. c) Eight new 0 - 15 A trim coil power supplies were ordered. d) Offer for new Teledyne Hastings flow meter power supply ENALL-P Digital Panel is CHF 2500. e) Andrea compared different target cell diameters in talks given in technical board and analysis meetings. The technical board discussed on this. One possibility would be to produce 40 mm diameter target cells for the proton runs in 2007 - 2008. Jaakko produced preliminary drawings for the 40 mm target cells: http://wwwcompass.cern.ch/compass/detector/target/na58ptdrawings/IM1.png http://wwwcompass.cern.ch/compass/detector/target/na58ptdrawings/IM2.png