Minutes from target meeting held on 11th of April 2003 in 892-1-B09 a) The planning for the following weeks was discussed. The magnet precooling was decided to start during the easter holidays, which would allow the target material loading between 23 - 25 April. Magnet LHe vessel needs to be flushed several times with Helium gas. 8 hours day shifts during the cool down will be organised. b) The NMR coils and cables were installed to the target holder by Kaori. She also moved the thermometers to have smallest coupling to the NMR circuit. Otherwise the thermometers are in the same position as in 2001. Jaakko put a small glassfiber tube in the upstream part of the 3He filling tube to remove the ground loop problem. The target holder was inserted into the cryostat, the noise level was ok, tuning of all channels can be done independently and no coupling to the thermometers was observed.