Minutes from target meeting held on 2nd of May 2003 in 888 a) The magnet was cooled down to 100 K with LN2 by 25th of April. The target material was successfully loaded on 24th of April with maximum temperature in mixing chamber about 110 K. During the weekend 26 - 27 April magnet was filled with LHe to the nominal level of 30 %. Nicolas Bourgeois was testing the magnet PSUs and protection system on 30th of April and 2nd of May. Finally the magnet was powered up to the full field on 2nd of May. b) Target loading platform was dropped on an accelerator magnet. It needs to be repaired for the target unloading in the end of the run. No damage was reported on the accelerator. c) The planning for the following weeks was discussed. TE-calibration will be started next Monday. On Sunday the mixing chamber will be filled with liquid 4He.